Beverwijk – Wijngaarden (NL)
Project
Microtunnelling for a gas pipeline project ID 1200 mm (“Gasrotonde”, Beverwijk-Wijngaarden)
Client
A.Hak Leidingbouw BV / Nederlandse Gasunie
Crossing
Roads, rivers; special points
Diameter
ID 1200 mm
Lengths
8 microtunnels, individual length between 72 m and 304 m, in total 1038 m
Execution
2013-2014
Remarks
PE coated gas pipes (steel pipes of 18m individual length) were microtunnelled without any casing pipe under roads, rivers, …After each jacking operation, a new pipe was welded, coated and tested